Summary
New fees — $300 for linear utility runs regardless of length and $100 for single-lot road opening connections — replace outdated $40 parcel-based charges, with clarifying wording still to come.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
Raises permit revenue from utilities like gas, water and fiber companies that previously paid as little as $40 per mile-long permit.
City taxpayers, since utility companies now bear more of the true permit administration cost.
Utility and fiber companies pay more; new-home builders face an added $100 connection fee.